TASK ORDER AGREEMENT FOR

 

SMALL SCALE SITES REMEDIATION PACKAGE
# 03*

 

 

 

TASK ORDER#: 541369

 

 

 

BETWEEN

 

CANADIAN NUCLEAR LABORATORIES LTD. /
LABORATOIRES NUCLÉAIRES CANADIENS LTÉE.

 

AND

 

PERMA-FIX CANADA INC.

 

 

 

*INFORMATION IN THIS DOCUMENT HAS BEEN EXCLUDED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 5413691 
 

 

PROTECTED SENSITIVE

 

1. Contract Title SMALL SCALE SITES REMEDIATION PACKAGE # 02
           
2. Task Order Execution Date April 30, 2019 3.

Task Order No.

Contractor shall use for all invoicing

541369
           
4. Framework Reference 507595 5. The Contract Type is: Fixed Price
           
6. Control Order No. Not Applicable 7. The Task Order Price is: $11,494,654.34
           
8. Contractor HST#   9. Currency is:

Canadian

           
10. The Site is: Municipality of Port Hope, Ontario 11. Price Schedule is provided in SCHEDULE 2
         
12. The Schedule and Key Dates : Per Schedule 3      
           
           
    The agreed Work Schedule is provided in Schedule 3
     

  13. The Task Order Term is as set out below:
             
  a) The Task Order Effective Date is: Upon Execution b) The Task Order Completion date is: December 16, 2019
             

14. Warranty Period

12 Months for commercial/residential properties from issue of CNL’s Certificate of Substantial Performance, and

 

24 Months for municipal properties from issue of CNL’s Certificate of Substantial Performance.

 

In accordance to MPH By-Law 50-2014 Phase 2 in Standard Operating Guideline Section 2.9

     
15. Addresses for Notices under this Task Order
   

a) CNL Representative(s) b) Contractor Representative
   

CNL at: Project Lead – Scott Schumacher

Email: scott.schumacher@cnl.ca

Cell:905-376-8913

 

With copy to: Tina Burghardt – tina.burghardt@cnl.ca

Contractor at [Address]

Email: John Kelly, jkelly@perma-fix.com

Cell: 865-313-3107

 

With copy to: Ben Nacarrato, bnaccarato@perma-fix.com

   
c) CNL Contracting Officer d) Contractor’s Supervisor
   

CNL at: Yvonne Rogers

Email: yvonne.rogers@cnl.ca

Tel: 905-885-8830, ext 45649

Contractor at [Address]

Email: Ray Cyr, rcyr@lakeland-multitrade.com

Cell: 905-375-8051

 

CNL Task Order No. 5413692 
 

PROTECTED SENSITIVE

 

16. Other communication: Not Applicable
     
17. Periods of Reply As specified in Schedule 1 and the Framework Agreement
     

This Task Order is issued pursuant to, and fully incorporates, the terms and conditions set forth within the governing Framework Agreement for Environmental Remediation Construction Works, No. 507935, with a Contract Date of 2017 October 18, by and between Canadian Nuclear Laboratories (CNL) and Milestone Environmental Contracting Inc.
 

 

Part 1: Description of the Work/Services
 

18.

Description of scope of Work

(Schedule 1)

In summary, Task Order Agreement is issued for remediation and construction work at specific sites within the Municipality of Port Hope, Ontario. These sites have been impacted with industrial waste and low-level radioactive waste (“LLRW”). The scope of work is summarized as follows (the “Work”):

     

    1. Remediation of a portion of the properties as per Specifications and Drawings Group 1B, 1C, !G, 1H and 1I (31 properties in total)
       
    2. The safe removal, collecting and verification of soil know to contain LLRW
       
    3. Transportation of waste along designated routes to the Long-Term Waste Management Facility (LTWMF) in the Municipality of Port Hope.
       
    4. Rehabilitation and Reconstruction/Restoration as per Specifications
       

    (Refer to Schedule 1)
     
19. Drawings & Documents Refer to Schedule 1
     
20. Deliverables As set out Schedule 1
     
21. Exclusions and Battery limits None
     
22. Assumptions and Risk Register As set out in Framework Agreement GC 6.1
     
23. Constraints or interdependencies Waste deliveries to the PH LTWMF must be coordinated with the LTWMF Contractor and CNL. This includes respective SOP’s and Owner’s access agreements between CNL and the Owners. As set out Schedule 1 – hours of operations.
     
24. CNL provided items and Rely-Upon Information Refer to Schedule 1 (as referred to in Appendix D of the RFP)

 

CNL Task Order No. 5413693 
 

PROTECTED SENSITIVE

 

Part 2: Key Data
 

25. Task Order Limits of Liability The Contractor’s limit of liability for this Task Order is: Task Order Price
       

    All in accordance with the provisions of the GC 11.4.2 of the Framework Agreement.
     
26.

Bonds and Guarantees

 

Performance Bond in accordance with GC 2.9 of the Framework Agreement in the amount of 50% of the Task Order Price.

 

Labour & Material Payment Bond in accordance with GC 2.9 of the Framework Agreement in the amount of 50% of the Task Order Price (at CNL’s request and discretion, to be determined upon award).

     
27. Insurances Insurance to be furnished in accordance with GC 10.1 of the Framework Agreement and as set out below:
     
    **Commercial General Liability coverage required: $ 5,000,000
     
    Automobile and Transportation Liability Insurance coverage required: $ 3,000,000
     
    Contractor’s Pollution Liability Insurance coverage required: $ 5,000,000
     
    Contractors Equipment Insurance (sufficient to cover all property, tools and equipment of the contractor)
     
    CNL AECL, and the Municipality shall appear as additional insureds and the policy will provide coverage for non-owned auto (if not otherwise covered below), mobile equipment, cross liability, blanket contractual liability, and an agreement by underwriters to waive rights of recourse against CNL, AECL and the Municipality. Coverage in the amount set out in this Task Order per occurrence will be maintained.
     
    Prior to award, the Contractor will have to add the Property Owner’s name on their Insurance Certificate and/or, if applicable the mortgagee’s name, CNL’s will provide all the information.
     
    Insurance to be provided and shall remain in effect in accordance with the terms of the Framework Agreement, Part 10.
     
28. Incentives Not applicable
     
29. Payment In accordance with the agreed Schedule of Values forming part of Schedule 2 and in accordance with the Framework Agreement, Article 5 Payment and Invoicing
       
30. Contractual Holdback The amount of Contractual Holdback applicable to this Task Order is: 10% in accordance with the Framework Agreement, Article 5.1(a)
       
31.

Delay Liquidated Damages

(if applicable)

Delay Liquidated Damages are: $5,000 per Working Day from Completion

 

The maximum Delay Liquidated Damages payable is: 10% of the Task Order Price

     
32. The Task Order Special Conditions are:  
     
33. Adjacent Operators Not Applicable

 

CNL Task Order No. 5413694 
 

PROTECTED SENSITIVE

Part 3: Contract Execution Requirements
 

34. HSSEQ Requirements As specified in Schedule 1
     
35. Quality Designation of Work As specified in Schedule 1
     
36. Training and Security As specified in Schedule 1
     
37. Codes, Standards & Regulatory Requirements As specified in Schedule 1
     
38. Performance, Communication and Reporting As specified in Schedule 8 – STAKEHOLDER ENGAGEMENT
     
39. Responsibilities As specified in the Framework Agreement
     
40. Reporting Requirements As specified in Schedule 1
     

Part 4: Schedules
 
Relevant documents to this Task Order.
 

  Schedule 1: Technical Statement of Work;
  Schedule 2: Price Schedule;
  Schedule 3: Work Schedule;
  Schedule 4: Special Conditions, Contractor’s Methodology
  Schedule 5: Subcontractors;
  Schedule 6: Field Equipment List;
  Schedule 7: Aboriginal and/or Local, Small and Medium-sized Business Engagement Plan
  Schedule 8 Contractor Stakeholder Engagement
     

Part 5: Execution of Task Order  
   
Canadian Nuclear Laboratories Perma-Fix Canada Inc.
   

Name/Position:

Mark Lesinski/President & CEO

 

Name/Position:  

Ben Naccarato, Vice President of Finance

       
Signature: /s/Mark Lesinski   Signature: /s/Ben Naccarato
         
Date: 6th May 2019   Date: 4-30-2019
         
Name/Position: Monica Steedman/VP Finance & CFO

  Name/Position:

PERMA-FIX DOES NOT REQUIRE A SECOND SIGNATORY

         
Signature: /s/Monica Steedman   Signature:

 

       
Date: 6th May 2019   Date:
         

 

CNL Task Order No. 5413695 
 

 

PROTECTED SENSITIVE

 

SCHEDULE 1 – TECHNICAL STATEMENT OF WORK

 

CNL Task Order No. 5413691Schedule 1
 

 

PROTECTED SENSITIVE

 

The Technical Statement of Work comprise the following:

 

4501-01340-TS-001, latest revision – Construction Package 3 Issued for Construction Specifications – Design Groups 1B, 1C, 1G, 1H and 1I in Port Hope, ON prepared by AMEC Foster Wheeler – .

 

4501-508120-MD-001, latest revision – Construction Package 3 Issued for Construction Drawings – Design Group 1B prepared by AMEC Foster Wheeler

 

4501-508120-MD-002, latest revision – Construction Package 3 Issued for Construction Drawings – Design Group 1G prepared by AMEC Foster Wheeler

 

4501-508120-MD-003, latest revision – Construction Package 3 Issued for Construction Drawings – Design Group 1C prepared by AMEC Foster Wheeler

 

4501-508120-MD-004, latest revision – Construction Package 3 Issued for Construction Drawings – Design Group 1H prepared by AMEC Foster Wheeler

 

4501-508120-MD-005, latest revision – Construction Package 3 Issued for Construction Drawings – Design Group 1I prepared by AMEC Foster Wheeler

 

In addition to the above, the following documents are hereby incorporated into and form part of this Task Oder by reference:

 

 

CNL Task Order No. 5413692Schedule 1
 

 

PROTECTED SENSITIVE

 

SCHEDULE 2 – PRICE SCHEDULE

 

CNL Task Order No. 5413691Schedule 2
 

 

PROTECTED SENSITIVE

 

Task Order Price

 

1. Unit Price quantities shown are estimates only. The associated unit prices will be used to calculate the actual value of Work performed. CNL makes no guarantee as to the quantities of Work to be actually performed by the Selected Proponent.

 

2. All lump sum pricing and unit pricing shall be firm, fixed and not subject to adjustment for the duration of the Task Order Term.

 

3. Note that where the items on the Pricing Form tab are inconsistent with the Measurement Procedures set out in the various Sections of the Specifications, the Pricing Form shall govern and take precedence over the Specifications.

 

4. Pricing for Labour Rates and Equipment Rates are in firm Canadian funds and will be adjusted annually in accordance with the Consumer Price Index (CPI) for the Province of Ontario (December of previous year to January of current year) using the following formula:

 

(December- current year/January - previous year)*100-100

 

The first annual adjustment of rates as set out above shall occur no sooner than eighteen months after the Effective Date.

 

5. Note that all Laboratory Analysis costs incurred by the Contractor for this project will be reimbursed at cost with no Contractor mark-up of any kind. Contractor’s invoices for third party laboratory costs shall include the actual costs incurred (not to exceed the Ceiling Price per Unit set out in the Pricing Form (for each chemical analysis performed) and shall be supported by the accredited laboratory’s ac

tual invoices paid by the Contractor for this project.

 

CNL Task Order No. 5413692Schedule 2
 

 

PROTECTED SENSITIVE

 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 5413693Schedule 2
 

PROTECTED SENSITIVE

 

   Specification Reference  Description  Unit of Measure  Estimated Quantity   Price per Unit   Total Price 
Group B - General Requirements                        
1  02 61 00  Mobilization and Project Startup  Lump Sum   1.00   $***   $*** 
2  02 61 00  Demobilization and Project Closeout  Lump Sum   1.00   $***   $*** 
3  01 31 19  Project Meetings  Lump Sum   1.00   $***   $*** 
4  01 32 00  Construction Progress Documentation  Lump Sum   1.00   $***   $*** 
5  01 32 16  Construction Progress Schedule  Lump Sum   1.00   $***   $*** 
6  01 35 29  Health and Safety Plan  Lump Sum   1.00   $***   $*** 
7  01 35 29  Implementation of Health and Safety - All Sites  Lump Sum   1.00   $***   $*** 
8  01 35 30  Radiation Protection Plan - All Sites  Lump Sum   1.00   $***   $*** 
9  01 35 30  Implementation of Radiation Protection - All Sites  Lump Sum   1.00   $***   $*** 
10  01 35 43  Environmental Protection Manual and Dust Management Plan - All Sites  Lump Sum   1.00   $***   $*** 
11  01 35 43  Implementation of Environmental Protection and Dust Management - All Sites  Lump Sum   1.00   $***   $*** 
12  01 45 00  Quality Assurance Plan  Lump Sum   1.00   $***   $*** 
13  01 45 00  Implementation of QA/QC - All Sites  Lump Sum   1.00   $***   $*** 
14  01 51 00  Provision and Maintenance of Temporary Utilities - (Contractor Use)  Lump Sum   1.00   $***   $*** 
15  01 52 00  Provision and Construction Facilities - All Sites  Lump Sum   1.00   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 5413694Schedule 2
 

PROTECTED SENSITIVE

 

16  02 61 00  Permitting as per OBC and MPH SOP-SOG, OMOECC, CN/CP - all sites  Lump Sum   1.00   $***   $*** 
17     Traffic Control - All sites  Lump Sum   1.00   $***   $*** 
18  01 33 00  All Other Submittals  Lump Sum   1.00   $***   $*** 
19  01 14 00  Site Security  Lump Sum   1.00   $***   $*** 
20     Bonding & Insurance  Lump Sum   1.00   $***   $*** 
21  01 14 00  Training and Security Clearance  Lump Sum   1.00   $***   $*** 
22  01 78 00  Closeout Submittal  Lump Sum   1.00   $***   $*** 
23  01 56 00  Supply, Install, Maintain, and Remove Sediment Erosion Control fencing  Linear meters   95   $***   $*** 
24  01 56 00  Supply, Install, Maintain, and Remove - Perimeter Safety Fencing  Linear meters   185   $***   $*** 
25  02 61 00  Supply, Install, Maintain and Remove Access Gates as shown  each   4   $***   $*** 
26  See Figure attached  Tree Protection Fencing  Linear meters   40   $***   $*** 
Total Price - General Requirements $*** 

 

Group B Requirements - 24 Smith Street

 

Removals                     
1  02 61 00  Pre-construction Property Condition Assessment  Lump Sum   1   $***   $*** 
2  02 61 00  Complete gamma survey and XRF scan of completed excavation surface  Lump Sum   1   $***   $*** 
3  02 61 00  Collection of soil sample for signature COPCs and the reporting of results following Laboratory Analysis  Lump Sum   1   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 5413695Schedule 2
 

PROTECTED SENSITIVE

 

4  02 61 00  Laboratory Analysis of soil sample for signature COPCs  Lump Sum   1   $***   $*** 
5  02 61 00  Collection of soil sample for secondary COPCs and the reporting of results following laboratory analysis  Lump Sum   1   $***   $*** 
6  02 61 00  Laboratory Analysis of composite soil sample for secondary COPCs  Lump Sum   1   $***   $*** 
7  02 61 00  Preparation and Submission of Verification Documentation  Lump Sum   1   $***   $*** 
8  02 41 16  Demolish Existing Site Structures that require removal, verify not radiologically impacted and dispose off site a licensed receiving facility  Lump Sum   1   $***   $*** 
9  02 41 13  Concrete Sidewalk Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq. meters   12   $***   $*** 
10  02 41 13  Concrete Stair Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
11  02 61 00  Remove and Dispose of Trees, shrubs, hedges, and all other plants above ground, verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
12  02 61 00  Remove all other surface landscape features, relocate offsite to secure location for future re-installment  Lump Sum   1   $***   $*** 
13  02 61 00  Excavate, stockpile, load, haul and dispose at LTWMF Facility Contaminated soil and tree roots  cubic meters   10   $***   $*** 
14     Secondary Excavation (if required)  cubic meters       $***      

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 5413696Schedule 2
 

PROTECTED SENSITIVE

 

Earthworks                        
1  31 00 01  Supply, place, compact and grade clean imported fill per MPH SOP/SOGs (based on 2 tonnes per cubic meter)  tonnes   2   $***   $*** 
2  31 00 01  Supply, place, compact and grade Granular A (based on 2 tonnes per cubic meter)  tonnes   4   $***   $*** 
3  31 00 01  Supply, place, compact and grade Granular B (based on 2 tonnes per cubic meter)  tonnes   4   $***   $*** 
4  31 00 01  Supply, place, and grade Topsoil  cubic meters   5   $***   $*** 
Site Restoration                        
1  as per Drawings  Supply and Place Concrete Sidewalk as per specifications  sq. meters   12   $***   $*** 
2  31 32 50  Water management, sampling, transportation, and disposal at LTMWF  Lump Sum   1.00   $***   $*** 
3  as per Drawings  Supply and Place concrete stairs as per specifications  treads   9   $***   $*** 
4  32 90 00  Landscape Restoration  Allowance   1   $***   $*** 
Total Price - 24 Smith $*** 

 

Group B Requirements - 26 Smith Street

 

Removals                     
1  02 61 00  Pre-construction Property Condition Assessment  Lump Sum   1   $***   $*** 
2  02 61 00  Complete gamma survey and XRF scan of completed excavation surface  Lump Sum   1   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 5413697Schedule 2
 

PROTECTED SENSITIVE

 

3  02 61 00  Collection of soil sample for signature COPCs and the reporting of results following Laboratory Analysis  Lump Sum   1   $***   $*** 
4  02 61 00  Laboratory analysis of soil sample for signature COPCs  Lump Sum   1   $***   $*** 
5  02 61 00  Collection of soil sample for secondary COPCs and the reporting of results following laboratory analysis  Lump Sum   1   $***   $*** 
6  02 61 00  Laboratory analysis of composite soil sample for secondary COPCs  Lump Sum   1   $***   $*** 
7  02 61 00  Preparation and submission of Verification Documentation  Lump Sum   1   $***   $*** 
8  02 41 13  Gravel Driveway Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   9   $***   $*** 
9  02 41 16  Demolish Existing Site Structures that require removal, verify not radiologically impacted and dispose off site a licensed receiving facility  Lump Sum   1   $***   $*** 
10  02 41 13  Concrete Sidewalk Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq. meters   23   $***   $*** 
11  02 41 13  Concrete Patio Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq. meters   40   $***   $*** 
12  31 11 00  Remove and Dispose of Trees, shrubs, hedges, and all other plants above ground, verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 5413698Schedule 2
 

PROTECTED SENSITIVE

 

13  02 61 00  Remove all other surface landscape features, relocate off-site to secure location for future re-installment  Lump Sum   1   $***   $*** 
14  02 61 00  Excavate, stockpile, load, haul and dispose at LTWMF Facility Contaminated soil and tree roots  cubic meters   60   $***   $*** 
15     Secondary Excavation (if required)  cubic meters       $***      
Earthworks                        
1  31 00 01  Supply, place, compact and grade clean imported fill per MPH SOP/SOGs (based on 2 tonnes per cubic meter)  tonnes   40   $***   $*** 
2  31 00 01  Supply, place, compact and grade Granular A (based on 2 tonnes per cubic meter)  tonnes   20   $***   $*** 
3  31 00 01  Supply, place, compact and grade Granular B (based on 2 tonnes per cubic meter)  tonnes   20   $***   $*** 
4  31 00 01  Supply, place, and grade Topsoil  cubic meters   20   $***   $*** 
Site Restoration                        
1  as per Drawings  Supply and Install covered porch as shown including all footings, etc., inluding all permits  square meters   22   $***   $*** 
2  as per Drawings  Supply, Place, Gravel Driveway as per specifications  square meters   9   $***   $*** 
2  as per Drawings  Supply and Place Concrete Sidewalk as per specifications  square meters   23   $***   $*** 
3  as per Drawings  Supply and Place Concrete Patio as per specifications  square meters   40   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 5413699Schedule 2
 

PROTECTED SENSITIVE

 

4  as per Drawings  Supply and Place concrete stairs as per specifications  treads   10   $***   $*** 
5  32 90 00  Landscape Restoration  Allowance   1   $***   $*** 
6  31 32 50  Water management, sampling, transportation, and disposal at LTMWF  Lump Sum   1.00   $***   $*** 
7  as per Drawings  Supply and Place Fence  Linear meters   25.00   $***   $*** 
Total Price - 26 Smith $*** 

 

Group B Requirements - 28 Smith Street

 

Removals                     
1  02 61 00  Pre-construction Property Condition Assessment  Lump Sum   1   $***   $*** 
2  02 61 00  Complete gamma survey and XRF scan of completed excavation surface  Lump Sum   1   $***   $*** 
3  02 61 00  Collection of soil sample for signature COPCs and the reporting of results following Laboratory Analysis  Lump Sum   1   $***   $*** 
4  02 61 00  Laboratory analysis of soil sample for signature COPCs  Lump Sum   1   $***   $*** 
5  02 61 00  Collection of soil sample for secondary COPCs and the reporting of results following laboratory analysis  Lump Sum   1   $***   $*** 
6  02 61 00  Laboratory analysis of composite soil sample for secondary COPCs  Lump Sum   1   $***   $*** 
7  02 61 00  Preparation and submission of Verification Documentation  Lump Sum   1   $***   $*** 
8  02 41 16  Demolish Existing Site Structures that require removal, verify not radiologically impacted and dispose off site a licensed receiving facility  Lump Sum   1   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136910Schedule 2
 

PROTECTED SENSITIVE

 

9  02 41 13  Concrete Sidewalk Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  square meters   23   $***   $*** 
10  02 41 13  Concrete Patio Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  square meters   40   $***   $*** 
11  02 41 13  Retaining Wall Removal - verify not radiologically impacted, offsite disposal at a licensed receiving facility, include all necessary support and bracing as required  Lump sum   1   $***   $*** 
12  02 41 13  Concrete Stair Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
13  31 11 00  Remove and Dispose of Trees, shrubs, hedges, and all other plants above ground, verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
14     Remove all other surface landscape features, relocate offsite to secure location for future re-installment  Lump Sum   1   $***   $*** 
15     Removal of Outbuilding Contents, storage in secured area, and return of objects upon restoration  Lump Sum   1   $***   $*** 
16  02 61 00  Excavate, stockpile, load, haul and dispose at LTWMF Facility Contaminated soil and tree roots  cubic meters   195   $***   $*** 
17     Secondary Excavation (if required)  cubic meters       $***      

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136911Schedule 2
 

PROTECTED SENSITIVE

 

Earthworks                        
1  31 00 01  Supply, place, compact and grade clean imported fill per MPH SOP/SOGs (based on 2 tonnes per cubic meter)  Tonnes   140   $***   $*** 
2  31 00 01  Supply, place, compact and grade Granular A (based on 2 tonnes per cubic meter)  Tonnes   50   $***   $*** 
3  31 00 01  Supply, place, compact and grade Granular B (based on 2 tonnes per cubic meter)  Tonnes   50   $***   $*** 
4  31 00 01  Supply, place, and grade Topsoil  cubic meters   75   $***   $*** 
Site Restoration                        
1  as per Drawings  Supply and Install detached Garage as shown including all footings, floors etc.  square meters   56   $***   $*** 
2  as per Drawings  Supply and Place Concrete Sidewalk as per specifications  square meters   23   $***   $*** 
3  as per Drawings  Supply and Place Concrete Patio as per specifications  square meters   40   $***   $*** 
4  as per Drawings  Supply and install Covered Porch (Rear) as shown including all permits  square meters   22   $***   $*** 
5  as per Drawings  Supply and Place Retaining Wall as per specifications  Linear meters   5   $***   $*** 
6  as per Drawings  Supply and Place concrete stairs as per specifications  treads   10   $***   $*** 
7  32 90 00  Landscape Restoration  Allowance   1   $***   $*** 
8  31 32 50  Water management, sampling, transportation, and disposal at LTMWF  Lump Sum   1.00   $***   $*** 
Total Price - 28 Smith $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136912Schedule 2
 

PROTECTED SENSITIVE

 

Group B Requirements - 30 Smith Street

 

Removals                     
1  02 61 00  Pre-construction Property Condition Assessment  Lump Sum   1   $***   $*** 
2  02 61 00  Complete gamma survey and XRF scan of completed excavation surface  Lump Sum   1   $***   $*** 
3  02 61 00  Collection of soil sample for signature COPCs and the reporting of results following Laboratory Analysis  Lump Sum   1   $***   $*** 
4  02 61 00  Laboratory analysis of soil sample for signature COPCs  Lump Sum   1   $***   $*** 
5  02 61 00  Collection of soil sample for secondary COPCs and the reporting of results following laboratory analysis  Lump Sum   1   $***   $*** 
6  02 61 00  Laboratory analysis of composite soil sample for secondary COPCs  Lump Sum   1   $***   $*** 
7  02 61 00  Preparation and submission of Verification Documentation  Lump Sum   1   $***   $*** 
8  02 41 16  Demolish existing Site structures that require removal, verify not radiologically impacted and dispose off site a licensed receiving facility  Lump Sum   1   $***   $*** 
9  02 41 13  Gravel Driveway Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   7   $***   $*** 
10  02 41 13  Concrete Sidewalk Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   14   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136913Schedule 2
 

PROTECTED SENSITIVE

 

11  02 41 13  Paving stone / interlocking brick patio Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  square meters   66   $***   $*** 
12  02 41 13  Retaining Wall Removal - verify not radiologically impacted, offsite disposal at a licensed receiving facility, include all necessary support and bracing as required  Lump sum   1   $***   $*** 
13  02 41 13  Concrete Stair Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
14  02 41 13  Remove existing fence, verify not radiologically impacted and dispose offiste at licensed receiving facility  Lump Sum   1   $***   $*** 
15  31 11 00  Remove and Dispose of Trees, shrubs, hedges, and all other plants above ground, verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
16     Remove all other surface landscape features, relocate offsite to secure location for future re-installment  Lump Sum   1   $***   $*** 
17     Removal of Outbuilding Contents, storage in secured area, and return of objects upon restoration  Lump Sum   1   $***   $*** 
18  02 61 00  Excavate, stockpile, load, haul and dispose at LTWMF Facility Contaminated soil and tree roots  cubic meters   425   $***   $*** 
19     Secondary Excavation (if required)  cubic meters       $***      

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136914Schedule 2
 

PROTECTED SENSITIVE

 

Earthworks                        
1  31 00 01  Supply, place, compact and grade clean imported fill per MPH SOP/SOGs (based on 2 tonnes per cubic meter)  tonnes   510   $***   $*** 
2  31 00 01  Supply, place, compact and grade Granular A (based on 2 tonnes per cubic meter)  tonnes   80   $***   $*** 
3  31 00 01  Supply, place, compact and grade Granular B (based on 2 tonnes per cubic meter)  tonnes   80   $***   $*** 
4  31 00 01  Supply, place, and grade Topsoil  cubic meters   90   $***   $*** 
Site Restoration                        
1  as per Drawings  Supply and Install Storage Sheds as shown including all footings, floors etc.  each   1   $***   $*** 
2  as per Drawings  Supply, Place, Gravel Driveway as per specifications  square meters   7   $***   $*** 
3  as per Drawings  Supply and Place Concrete Sidewalk as per specifications  square meters   14   $***   $*** 
4  as per Drawings  Supply, Place Covered Porch (Front) as shown including all permits  square meters   23   $***   $*** 
5  06 15 00  Supply, Place Wooden deck (Rear) as shown including all permits  square meters   18   $***   $*** 
6  as per Drawings  Supply and Place Paving Stone / Interlocking Brick Patio Patio as per specifications  square meters   66   $***   $*** 
7  as per Drawings  Supply and Place Retaining Wall as per specifications  Linear meters   25   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136915Schedule 2
 

PROTECTED SENSITIVE

 

8   as per Drawings   Supply and Place concrete stairs as per specifications   treads     6     $ ***     $ ***  
9   31 32 50   Water management, sampling, transportation, and disposal at LTMWF   Lump Sum     1.00     $ ***     $ ***  
10   as per Drawings   Supply and Place Fence   Linear meters     26     $ ***     $ ***  
11   32 90 00   Landscape Restoration   Allowance     1     $ ***     $ ***  
Total Price - 30 Smith $ ***  
       
Total Remediation, Earthworks and Restoration Only $ ***  

 

   Specification Reference  Description  Unit of Measure  Estimated Quantity   Price per Unit   Total Price 
Group C - General Requirements                        
1  02 61 00  Mobilization and Project Startup  Lump Sum   1.00   $***   $*** 
2  02 61 00  Demobilization and Project Closeout  Lump Sum   1.00   $***   $*** 
3  01 31 19  Project Meetings  Lump Sum   1.00   $***   $*** 
4  01 32 00  Construction Progress Documentation  Lump Sum   1.00   $***   $*** 
5  01 32 16  Construction Progress Schedule  Lump Sum   1.00   $***   $*** 
6  01 35 29  Health and Safety Plan  Lump Sum   1.00   $***   $*** 
7  01 35 29  Implementation of Health and Safety - All Sites  Lump Sum   1.00   $***   $*** 
8  01 35 30  Radiation Protection Plan - All Sites  Lump Sum   1.00   $***   $*** 
9  01 35 30  Implementation of Radiation Protection - All Sites  Lump Sum   1.00   $***   $*** 
10  01 35 43  Environmental Protection Manual and Dust Management Plan - All Sites  Lump Sum   1.00   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136916Schedule 2
 

PROTECTED SENSITIVE

 

11  01 35 43  Implementation of Environmental Protection and Dust Management - All Sites  Lump Sum   1.00   $***   $*** 
12  01 45 00  Quality Assurance Plan  Lump Sum   1.00   $***   $*** 
13  01 45 00  Implementation of QA/QC - All Sites  Lump Sum   1.00   $***   $*** 
14  01 51 00  Provision and Maintenance of Temporary Utilities - (Contractor Use)  Lump Sum   1.00   $***   $*** 
15  01 52 00  Provision and Construction Facilities - All Sites  Lump Sum   1.00   $***   $*** 
16  02 61 00  Permitting as per OBC and MPH SOP-SOG, OMOECC, CN/CP - all sites  Lump Sum   1.00   $***   $*** 
17     Traffic Control - All sites  Lump Sum   1.00   $***   $*** 
18  01 33 00  All Other Submittals  Lump Sum   1.00   $***   $*** 
19  01 14 00  Site Security  Lump Sum   1.00   $***   $*** 
20     Bonding & Insurance  Lump Sum   1.00   $***   $*** 
21  01 14 00  Training and Security Clearance  Lump Sum   1.00   $***   $*** 
22  01 78 00  Closeout Submittal  Lump Sum   1.00   $***   $*** 
23  01 56 00  Supply, Install, Maintain, and Remove Sediment Erosion Control fencing  Linear meters   165   $***   $*** 
24  01 56 00  Supply, Install, Maintain, and Remove - Perimeter Safety Fencing  Linear meters   330   $***   $*** 
25  02 61 00  Supply, Install, Maintain and Remove Access Gates as shown  each   6   $***   $*** 
26  See Figure Attached  Tree Protection Fencing  Linear meters   180   $***   $*** 
Total Price - General Requirements $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136917Schedule 2
 

PROTECTED SENSITIVE

 

Group C Requirements - 21 Elizabeth Street

 

Removals                     
1  02 61 00  Pre-construction Property Condition Assessment  Lump Sum   1   $***   $*** 
2  02 61 00  Complete gamma survey and XRF scan of completed excavation surface  Lump Sum   1   $***   $*** 
3  02 61 00  Collection of soil sample for signature COPCs and the reporting of results following Laboratory Analysis  Lump Sum   1   $***   $*** 
4  02 61 00  Laboratory Analysis of soil sample for signature COPCs  Lump Sum   1   $***   $*** 
5  02 61 00  Collection of soil sample for secondary COPCs and the reporting of results following laboratory analysis  Lump Sum   1   $***   $*** 
6  02 61 00  Laboratory Analysis of composite soil sample for secondary COPCs  Lump Sum   1   $***   $*** 
7  02 61 00  Preparation and Submission of Verification Documentation  Lump Sum   1   $***   $*** 
8  02 41 16  Demolish Existing Site Structures that require removal, verify not radiologically impacted and dispose off site a licensed receiving facility  Lump Sum   1   $***   $*** 
9  02 41 13  Gravel Driveway Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   11   $***   $*** 
10  02 41 13  Concrete Sidewalk Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   9   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136918Schedule 2
 

PROTECTED SENSITIVE

 

11  02 41 13  Remove existing fence, verify not radiologically impacted and dispose offiste at licensed receiving facility  Lump Sum   1   $***   $*** 
12  02 61 00  Remove and Dispose of Trees, shrubs, hedges, and all other plants above ground, verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
13  02 61 00  Remove all other surface landscape features, relocate offsite to secure location for future re-installment  Lump Sum   1   $***   $*** 
14  02 61 00  Removal of Outbuilding Contents, storage in secured area, and return of objects upon restoration  Lump Sum   1   $***   $*** 
15  02 61 00  Excavate, stockpile, load, haul and dispose at LTWMF Facility Contaminated soil and tree roots  cubic meters   165   $***   $*** 
16     Secondary Excavation (if required)  cubic meters       $***      
Earthworks                        
1  31 00 01  Supply, place, compact and grade clean imported fill per MPH SOP/SOGs (based on 2 tonnes per cubic meter)  tonnes   120   $***   $*** 
2  31 00 01  Supply, place, compact and grade Granular A (based on 2 tonnes per cubic meter)  tonnes   40   $***   $*** 
3  31 00 01  Supply, place, compact and grade Granular B (based on 2 tonnes per cubic meter)  tonnes   40   $***   $*** 
4  31 00 01  Supply, place, and grade Topsoil  cubic meters   65   $***   $*** 
Site Restoration                        

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136919Schedule 2
 

PROTECTED SENSITIVE

 

1  as per Drawings  Supply and Install shed as shown including all footings, etc., inluding all permits  square meters   4   $***   $*** 
2  as per Drawings  Supply and Place Gravel Drivway as per specifications  square meters   11   $***   $*** 
3  as per Drawings  Supply and Place Concrete Sidewalk as per specifications  square meters   9   $***   $*** 
4  31 32 50  Water management, sampling, transportation, and disposal at LTMWF  Lump Sum   1.00   $***   $*** 
5  32 90 00  Landscape Restoration  Allowance   1   $***   $*** 
6  as per Drawings  Supply and Place Fence  Linear meters   15.00   $***   $*** 
Total Price - 21 Elizabeth Street $*** 

 

Group C Requirements - 11-15 Elizabeth Street

 

Removals                     
1  02 61 00  Pre-construction Property Condition Assessment  Lump Sum   1   $***   $*** 
2  02 61 00  Complete gamma survey and XRF scan of completed excavation surface  Lump Sum   1   $***   $*** 
3  02 61 00  Collection of soil sample for signature COPCs and the reporting of results following Laboratory Analysis  Lump Sum   1   $***   $*** 
4  02 61 00  Laboratory analysis of soil sample for signature COPCs  Lump Sum   1   $***   $*** 
5  02 61 00  Collection of soil sample for secondary COPCs and the reporting of results following laboratory analysis  Lump Sum   1   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136920Schedule 2
 

PROTECTED SENSITIVE

 

6  02 61 00  Laboratory analysis of composite soil sample for secondary COPCs  Lump Sum   1   $***   $*** 
7  02 61 00  Preparation and submission of Verification Documentation  Lump Sum   1   $***   $*** 
8  02 41 16  Demolish Existing Site Structures that require removal, verify not radiologically impacted and dispose off site a licensed receiving facility  Lump Sum   1   $***   $*** 
9  02 41 13  Concrete Sidewalk Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   5   $***   $*** 
10  02 41 13  Gravel Driveway Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   7   $***   $*** 
11  02 41 13  Remove existing fence, verify not radiologically impacted and dispose offiste at licensed receiving facility  Lump Sum   1   $***   $*** 
12  02 41 13  Concrete Stair Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
13  31 11 00  Remove and Dispose of Trees, shrubs, hedges, and all other plants above ground, verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
14  02 61 00  Remove all other surface landscape features, relocate offsite to secure location for future re-installment  Lump Sum   1   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136921Schedule 2
 

PROTECTED SENSITIVE

 

15  02 61 00  Removal of Outbuilding Contents, storage in secured area, and return of objects upon restoration  Lump Sum   1   $***   $*** 
16  02 61 00  Excavate, stockpile, load, haul and dispose at LTWMF Facility Contaminated soil and tree roots  cubic meters   330   $***   $*** 
17     Secondary Excavation (if required)  cubic meters       $***      
Earthworks                        
1  31 00 01  Supply, place, compact and grade clean imported fill per MPH SOP/SOGs (based on 2 tonnes per cubic meter)  tonnes   520   $***   $*** 
2  31 00 01  Supply, place, compact and grade Granular A (based on 2 tonnes per cubic meter)  tonnes   40   $***   $*** 
3  31 00 01  Supply, place, compact and grade Granular B (based on 2 tonnes per cubic meter)  tonnes   40   $***   $*** 
4  31 00 01  Supply, place, and grade Topsoil  cubic meters   30   $***   $*** 
Site Restoration                        
1  as per Drawings  Supply and Install wooden deck as shown including all footings, etc., inluding all permits  square meters   29   $***   $*** 
2  as per Drawings  Supply and Place Gravel Drivway as per specifications  square meters   7   $***   $*** 
3  as per Drawings  Supply and Place Concrete Sidewalk as per specifications  square meters   5   $***   $*** 
4  as per Drawings  Supply and Place concrete stairs as per specifications  treads   7   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136922Schedule 2
 

PROTECTED SENSITIVE

 

5  31 32 50  Water management, sampling, transportation, and disposal at LTMWF  Lump Sum   1.00   $***   $*** 
6  32 90 00  Landscape Restoration  Allowance   1   $***   $*** 
7  as per Drawings  Supply and Place Fence  Linear meters   18.00   $***   $*** 
Total Price - 11-15 Elizabeth Street $*** 

 

Group C Requirements - 9 Elizabeth Street

 

Removals                     
1  02 61 00  Pre-construction Property Condition Assessment  Lump Sum   1   $***   $*** 
2  02 61 00  Complete gamma survey and XRF scan of completed excavation surface  Lump Sum   1   $***   $*** 
3  02 61 00  Collection of soil sample for signature COPCs and the reporting of results following Laboratory Analysis  Lump Sum   1   $***   $*** 
4  02 61 00  Laboratory analysis of soil sample for signature COPCs  Lump Sum   1   $***   $*** 
5  02 61 00  Collection of soil sample for secondary COPCs and the reporting of results following laboratory analysis  Lump Sum   1   $***   $*** 
6  02 61 00  Laboratory analysis of composite soil sample for secondary COPCs  Lump Sum   1   $***   $*** 
7  02 61 00  Preparation and submission of Verification Documentation  Lump Sum   1   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136923Schedule 2
 

PROTECTED SENSITIVE

 

8  02 41 16  Demolish Existing Site Structures that require removal, verify not radiologically impacted and dispose off site a licensed receiving facility  Lump Sum   1   $***   $*** 
9  02 41 13  Gravel Driveway Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   42   $***   $*** 
10  02 41 13  Concrete Sidewalk Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   5   $***   $*** 
11  02 41 13  Paving Stone / Interlocking Brick Sidewalk Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   24   $***   $*** 
12  02 41 13  Paving Stone / Interlocking Brick Patio Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  sq.meters   11   $***   $*** 
13  02 41 13  Concrete Stair Removal - verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
14  02 41 13  Remove existing fence, verify not radiologically impacted and dispose offiste at licensed receiving facility  Lump Sum   1   $***   $*** 
15  02 41 13  Remove existing Retaining wall, verify not radiologically impacted and dispose offiste at licensed receiving facility          $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136924Schedule 2
 

PROTECTED SENSITIVE

 

16  31 11 00  Remove and Dispose of Trees, shrubs, hedges, and all other plants above ground, verify not radiological impacted and dispose offsite at a licensed receiving facility  Lump Sum   1   $***   $*** 
17  02 41 13  Remove all other surface landscape features, relocate offsite to secure location for future re-installment  Lump Sum   1   $***   $*** 
18  02 41 13  Removal of Outbuilding Contents, storage in secured area, and return of objects upon restoration  Lump Sum   1   $***   $*** 
19  02 61 00  Excavate, stockpile, load, haul and dispose at LTWMF Facility Contaminated soil and tree roots  cubic meters   340   $***   $*** 
20     Secondary Excavation (if required)  cubic meters       $***   $*** 
Earthworks                        
1  31 00 01  Supply, place, compact and grade clean imported fill per MPH SOP/SOGs (based on 2 tonnes per cubic meter)  tonnes   360   $***   $*** 
2  31 00 01  Supply, place, compact and grade Granular A (based on 2 tonnes per cubic meter)  tonnes   60   $***   $*** 
3  31 00 01  Supply, place, compact and grade Granular B (based on 2 tonnes per cubic meter)  tonnes   60   $***   $*** 
4  31 00 01  Supply, place, and grade Topsoil  cubic meters   100   $***   $*** 
Site Restoration                        
1  as per Drawings  Supply and Place Gravel Driveway as per specifications  square meters   42   $***   $*** 

 

***INDICATES CERTAIN INFORMATION IN THIS DOCUMENT WHICH HAS BEEN OMITTED FROM THIS PUBLIC FILING BECAUSE IT IS NOT MATERIAL AND WOULD LIKELY CAUSE COMPETITIVE HARM TO THE COMPANY IF PUBLICLY DISCLOSED.

 

CNL Task Order No. 54136925Schedule 2
 

PROTECTED SENSITIVE

 

<
2  as per Drawings  Supply and Place Concrete Sidewalk as per specifications  square meters   5   $***   $*** 
3  as per Drawings  Supply and Place Paving Stone / Interlocking Brick Sidewalk as per specifications  square meters   24